|
PART FIVE SIZING THE DEHUMIDIFIER
When deciding what size Dehumidifier to use, remember
that controlled space requirements sometimes exceed the anticipated design
peak load. Unusual and unforseen humidity loads-such as from abnormal weather
conditions or the introduction of high-moisture content raw materials-can
burden the drying equipment. Here we present
a number of issues that must be considered in approaching and solving specific
drying problems. Six typical humidity control example are presented:
- Food and drug manufacturing, specifically
raw materials and processing equipment (Production of hard candy)
- Storage or equipment areas (Standby warehouse)
- Product drying
- Controlled humidity and temperature areas
- Specific purposes for dry air production
- Prevention of condensation (Water treatment
plant)
Note: Dehumidifier performance used in these examples can be found in
Appendix 4.
EXAMPLE 1: PRODUCTION OF HARD CANDY
During the candy and cough drop production, the
material is in a plastic state. It must flow and be shaped by stamping
machines. If the presence of excess moisture causes the material to become
sticky, it will not flow freely and it will adhere to the stamping machine.
To eliminate this material and equipment problem,
dry the surrounding air.
Physical Facts
- Area to be conditioned - 60' x 42' x 16'
- Outside Design Condition - 95°F db*;
75°F wb*
- Controlled Space requirement** - 75°F
db;35 percent RH
- Physical Openings - 1 door(6' x 7'); opened
6 times/hr
- Number of people working in area - 10
- Construction - 8" masonry
- Make-up air specified by owner - 350cfm
* db = dry bulb value; wb = wet bulb value
** See Appendix 5.
Problem
To determine the size of dehumidifier necessary to maintain the desired
controlled space conditions.
Assumptions
1. The door is adequately weather stripped and
is of standard construction.
2. Ten workers in the area maintain a moderate pace; each requires ventilating
air.
3. The interior of the control space is constructed with two coats of
vapor barrier paint.
4. There are no other openings in and out of the controlled space.
5. All physical cracks are sealed.
6. A vapor barrier is provided in or under the concrete floor.
Space Moisture Loads to be Computed
1. Permeation load
2. Load through the door
3. Population load
| PERMEATION LOAD |
V
x
G x F1
x F2 x F3
x F4 = Grains per hour
C |
| V |
=
|
60 x 42 x 16 = 40,320 ft.3 |
| C |
=
|
14 (Specific volume of dry air @ 95°F) |
G |
=
|
75 grs/lb, outside design wet bulb of
75°F gives 121 gr/lb from Table I. Controlled space requirement
of 75°F db, 35% rh yields 46 grains per pound from a standard
Psychrometric chart. Therefore, 121-46=75 grs/lb. |
| F1 |
=
|
1.94 |
From Table II |
Factor for moisture difference
of 75 gr/lb - interpolated |
| F2 |
=
|
.5 |
From Table III |
|
| F3 |
=
|
1.0 |
From Table IV |
Factor for 8" masonry |
| F4 |
=
|
.75 |
From Table IV |
Factor for 2 coats of paint |
40,320 x 75 x 1.94 x .5 x 1.0
x .75 = 157,140 grs/hour
14 |
| DOOR LOAD |
Ohr x A
x G x F1
= grs/hr
C |
| Ohr |
=
|
6 |
| A |
=
|
6 x 7 = 42 sq ft |
| C |
=
|
7 |
G |
=
|
75 grs/lb |
| F1 |
=
|
1.94 |
6 x 42 x 75 x 1.94 = 5,238 gr/hr
7 |
POPULATION LOAD
At a db of 75°F and working at a moderate rate, a person will
expel 2,540 grains each hour. (See Appendix 3)
Therefore ten people will add 10 x 2,540 = 25,400 grains each hour
| TOTAL LOAD |
|
157,140
|
grs/hr
|
Permeation |
|
5,238
|
grs/hr
|
Through door |
|
25,400
|
grs/hr
|
Population load |
|
187,778
|
grs/hr
|
Total |
The drying system and load requirement are
shown in the schematic below:

Note that 350-cubic feet per minute (cfm) outside air is based on a requirement
of 30 cfm for each of the 10 workers is introduced at the dehumidifier.
The effect of this air on the ultimate dehumidifier size will be handled
below. Proceed with the following calculation:
X = C x ( gr/hr) / (S-G)
60
Where : X =
Delivery air fate from dryer to space in cfm
gr/hr
= Total moisture load in grain per hour in the space
C=14
= constant
S=
46 = Grs/lb moisture requirement of controlled space. In the absence of
a ventilation requirement this would be the inlet
condition
at the dryer.
G=
Grs/lb of air leaving dryer. Refer to Chart 1, Appendix 4, Enter curve
at 46 grain "Inlet moisture condition." Intersect 75°
Inlet
air temp curve at 14 gr/lb
14
x (187,778) / (46 -14)=1369 cfm
60
From the above calculation the space moisture
load is 187,778 gr/min. 1369 cfm air at 14 grs/lb will maintain the space
design conditions.
At this stage in the procedure, it is necessary to resort to the method
of approximation to select the correct dryer.
In addition to handling the space load the dryer
must handle the moisture load contributed by the 350 cfm outside air requirement.
So use a 2000 cfm Bry-Air Dryer (MVB-20C or FVB 4000).
If the dryer has a delivery rate of 2000 cfm, and if 350 cfm of outside
air is to be introduced, there remains 1650 cfm of air from the conditioned
space. Tabulate this air mixture
350 cfm x 121 gr/lb = 42,350
1650 cfm x 46 gr/lb = 75,900
2000 cfm 118,250
Then 118,250 = 59.1 grs/lb
2000
Refer again to Chart 1, Appendix 4, it shows
that air entering the dryer at 59.1 grs/lb would leave the dryer at approximately
23 grs/lb. (NOTE: Interpolate between the 75° and 85° curves since the
air is a mixture of 75°F and 95°F = 79° F.)
Total moisture pickup X (S - G) x 60 - Total Moisture Pickup
C
2000 x (46-23) x 60 = 197,143 grs/hr total removal capacity
14
The following work sheet is a demonstration of what the calculations
will look like.
In the above calculations, moisture gain or air leakage in the process
ductwork was not considered. If, however, the process and return ductwork
did contribute to the moisture load, the total duct volume would be an
additional space. Then the permeation calculation on page 9 would be used:
V = duct volume; C = 14; F1 from Table II,
with moisture difference G
measured from inside process air duct to surround ambient; F3
for tight, good commercial ductwork = 0.6. Add the resultant moisture
gain to the room total load. A nominal allowance for process air lost
due to duct leakage = 5 percent.
Recommendation
Selecting an MVB-20C or FVB-4000 at 2000
CFM is the best choice for the hard candy manufacturing example. While
it may seem to be an oversized selection, consider that all desiccants
in all manufacturers' desiccant dryers will age, will possibly become
physically and chemically contaminated with dirt, dust, or chemicals,
and will gradually lose their effectiveness. Fortunately, with the MVB-20C
or FVB-4000, higher levels of moisture in the leaving air upto
24 grs/lb dry air could be tolerated prior to a desiccant change. So what
appears to be an oversized selection would actually allow much longer
use of a desiccant charge or rotor and provide the economies of longer
use.
BRY-AIR DEHUMIDIFIER CALCULATION SHEET
PROJECT: EXAMPLE 1 - PRODUCTION OF HARD CANDY
Calculation
Sheet
Example
II: STANDBY WAREHOUSE
Moisture damage in a standby or storage warehouse can be avoided by surrounding
the machinery, equipment, or material with dry air.
Physical Facts
- Area to be conditioned - 210' x 176' x 45'
= 1,663,200 cubic feet
- Outside design condition - 95°F db; 77°F
wb
- Controlled space requirement* - 85°F
db; 40 percent rh
- No physical openings nor appreciable amount
of door openings or closing specified
- No people working in the area
- Construction - 8" masonry.
* See Appendix 5
Problem
To determine the size of the dehumidifier required
to maintain standby conditions.
Assumptions
- All physical cracks are seated and the floor properly vapor-proofed.
- If the room is completely vapor-proofed, use Table 4 on page 8.
- Two coats of vapor barrier paint have been applied externally for
metal clad construction.
* External application is recommended because:
- Outside walls are usually easier to access
than inside walls for paint application.
- Coating the outside walls discourages water
permeation into the wall and thus minimizes water accumulation in the
wall structure itself.
Space Moisture Loads to be Computed
- Permeation load
- Moisture Load
The Permeation Load is the only moisture load involved in this example.
V x G
x F1
x F2 x F3
x F4 = grains per hours
C
| Where: |
| V |
=
|
210 x 176 x 45= 1,663,200 cubic feet |
| C |
=
|
14 = Constant |
G |
=
|
58 grs/lb, outside design wet bulb of
77°F gives 130 gr/lb from Table I page 8. Controlled space
requirement of 85°F db, 40% rh
yields 72 grs/lb from a standard Psychrometric chart. Therefore,
130-72=58. |
| F1 |
=
|
1.54 from Table II |
-Factor for moisture difference of 63grs/lb |
| F2 |
=
|
0.24 from Table III |
-extrapolated as straight line for a
volume of 1,663,200 cubic feet |
| F3 |
=
|
1.0 from Table IV |
-Factor for 8" masonry |
| F4 |
=
|
.75 from Table IV |
-Factor for 2 coats of paint |
1,663,200
x 58 x 1.54 x 0.24 x 1.0 x 0.75 = 1,910,019 grs/lb.
14
|
Refer to schematic below, which shows the load requirements and drying
system.
X= C x (gr/hr) / (S-G)
60
|
| Where |
X |
=
|
cfm delivery air rate from dryer |
| |
C |
=
|
14 (constant) |
| |
S |
=
|
72 grs/lb moisture requirement of controlled
space |
| |
G |
=
|
grs/lb in air leaving the dryer. Refer to Chart1, Appendix 4.
Enter curve at 72° 'Inlet moisture condition'. Interpolate 'Inlet
Air Temperature Curve' between 75° and 95° and find
"leaving moisture" at 33 grs/lb
|
| |
X |
=
|
14 x (1,910,019) / (72 - 33) |
| |
|
|
60 |
| |
X |
=
|
11,427 cfm |
Therefore 11,427 cfm of air (33 gr/lb) from the dehumidifier
is needed to maintain a grain level of 72 gr/lb.
In a building of this size and shape , air distribution ducts are practical
for effectively spreading the air so it can return to a common point and
re-enter the dehumidifier.
Recommendation
Use one Bry-Air FLB-25000 or MVB-125E Dehumidifier at 12,500 CFM
in this standby warehouse example with a fan sized to handle the necessary
static pressure of the duct system.
BRY- AIR DEHUMIDIFIER CALCULATION SHEET
PROJECT: EXAMPLE II - STANDBY WAREHOUSE
Calculation
Sheet
Example
III: Product Drying
Here we have a room used to remove water vapor from such products as cattle
feed mixes, nylon or rayon cord for tires, raw plastic material, granular
chemicals, raw paper stock, cardboard stock for coatings, or other similar
products.
In this example, the room is used for drying cattle feed mixes, which
are contained on drying carts that stand in the room until the specified
level of dryness is attained.
Space condition requirements and product movement rate are determined
by the manufacturer.
Physical Facts
- Drying room size - 40' x 65' x 16'
- Outside design condition - 93°F; db; 73°F wb
- Controlled space requirement - 95°F; 15 percent rh (36 gr/lb)
- One double door; (a) 6' x 7' (b) Opens at 2 times/hr
- There are no other openings
- There are no workers in room except to bring mix in and out
- Product movement rate - 1500 lb/hr (i.e. carts with trays of mix are
moved into the drying room at the rate of 1500 lb/hr)
- Product enters room at 8 percent moisture and leaves at 4 percent
moisture
- Drying room wall construction - 8" masonry
- 350 cfm outside air required by manufacturer
Problem
To determine the size of dehumidifier
Assumptions
- All physical cracks are sealed.
- The double door is weather stripped.
- Two coats of vapor barrier paint have been applied to the wall and
ceiling construction of the drying room; the floor is suitably protected
against vapor permeation.
Moisture Loads to be Computed
1. Product load
2. Permeation load
3. Door load
Product Load:
Since the product will lose 4 percent moisture (by weight) and there are
1500 pounds of product each hour:
1500 lb/hr x (8 % - 4 %) = 60 lb/hr water removal
Since one pound of water equals 7000 grains, then:
60 x 7000 = 420,000 gr/hr product load
Note that the time needed to reduce the material to a 4 percent moisture
level would have to be given or experimentally determined. This would
then decide the amount of material to process and the size of the drying
chamber needed.
| PERMEATION LOAD |
|
V x G
x F1
x F2 x F3
x F4
C |
= Grains per hour |
| V |
=
|
40' x 65' x 16' |
= 41,600 cu ft. |
| C |
=
|
14 constant |
|
G |
=
|
77 gr/lb, outside design wb of 73°F
gives 113 gr/lb. from Table-1. Drying room space requirement of
95°F, 15% rh yields 36 gr/lb from the Psychrometric Chart. |
| F1 |
=
|
1.99 From Table II |
- Factor for moisture difference of 84
grains. |
| F2 |
=
|
0.50 From Table III |
- Permeation factor |
| F3 |
=
|
1.0 From Table IV |
- Factor for 8" masonry. |
| F4 |
=
|
0.75 From Table IV |
- Factor for 2 coats paint. |
|
41,600 x 77 x 1.99 x 0.50 x 1.0 x 0.75
14
|
= grs/hr
= 170,742 grs/hr |
| DOOR LOAD |
|
| Ohr |
=
|
A x G
x F1
C |
= grs/hr |
| Ohr |
=
|
2 |
|
| A |
=
|
6' x 7' |
= 42 sq. ft. |
| C |
=
|
7 (constant) |
|
G |
=
|
77 grs/lb |
|
| F1 |
=
|
1.99 From Table II - Factor for moisture
difference of 84 grains. |
2 x 42 x 77 x 1.99 = grs/hr.
7
= 1839 grains
|
Total Moisture Load
|
420,000
|
gr/hr
|
Product Load |
|
170,742
|
gr/hr
|
Permeation Load |
|
1,839
|
gr/hr
|
Door Load |
 |
|
592,581
|
gr/hr
|
Total Moisture Load |
The 350 cfm outside air requirement will be considered at a later stage
in the calculation.
Proceed with calculation as follows:
X
= C x (gr/hr) / (S-G)
60
| Where |
X |
=
|
cfm - air rate from dryer |
| |
C |
=
|
14 (constant) |
| |
S |
=
|
36 = grs/lb drying room controlled
space requirement. In the absence of an outside air requirement this
would be the inlet condition at dryer. |
| |
G |
=
|
15 gr/lb - equals condition of air leaving dryer. Refer to Chart
1, appendix 4. enter curve at 36 - intersect 95°F curve
at 15 gr/lb
|
| |
X |
=
|
14 x (592,321) / (36 - 15) |
| |
|
|
60 |
| |
X |
=
|
6584 cfm |
Recommendation
The Bry-Air MVB-75E or FLB 12500 Dehumidifier, rated at 7500 cfm,
should be adequate. However, the first step should be to determine if
this Dehumidifier has enough capacity to handle the 350 cfm outside air
in addition to the moisture load in the drying room.
If the dryer has a delivery rate of 7500 cfm and 350 cfm of outside air
is to be introduced, there remains 7150 cfm from the conditioned space.
Tabulate this air mixture as follows:
350 cfm x 113 gr/lb = 39,550
7150 cfm x 36 gr/lb 257,400
7500 296,950
296,950 = 39.6 gr/lb
7500
Reference to Chart 1, Appendix 4, shows that
air entering the dryer at 39.5 gr/lb would leave at 17 gr/lb
7500 x (39.6 -17) x 60 = 726,285 gr/hr
14
The computed moisture load is 592,581 gr/hr. Therefore, the MVB-75E
or FLB 12500 is adequate to handle the moisture load.
BRY- AIR DEHUMIDIFIER CALCULATION SHEET
PROJECT: EXAMPLE III - STANDBY WAREHOUSE
Calculation
Sheet
Example IV: CONTROLLED HUMIDITY
AND TEMPERATURE AREAS
Many air conditioned manufacturing areas often have a required air flow
to handle a sensible load in that space. This air quantity requirement
and the accompanying dehumidifier size are usually greater` than those
needed to handle a latent load.
By designing, a system for the sensible load situation and then determining
the appropriate dehumidifier to handle the moisture load, the desired
conditions for the space can be maintained.
Physical Facts
1. Area to be conditioned - 62.5' x 55' x 14'
2. Outside design conditions - 95°F db; 77°F wb
3. Controlled space requirement - 55°F db; 30 percent rh; 20 gr/lb
4. Door - 1 (6' x 8'), 6 openings/hr; 1 (3' x7'), 4 openings/hr
5. Other (fixed) openings - 2.8 sq. ft., w/tunnel 10' deep
6. Number of people working in area - 10
7. Air required for sensible temperature control - 24,715 cfm, 42°F
8. Construction - Block walls; drywall ceiling with vapor proofing; concrete
floor on grade
9. Make-up air required - 2400 cfm
10. Air available for make-up - 50°F db/49°F wb; 50 gr/lb.
Problem
To determine the size of the dehumidifier needed in a controlled humidity
and temperature area.
Moisture Load to be Computed
1. Permeation
2. Load through doors
3. Load through fixed openings
4. Population load
PERMEATION LOAD
V x G
x F1
x F2 x F3
x F4 = grains per hour
C |
| V |
=
|
62.5' x 55' x 14' = 48,125 cu. ft. |
| C |
=
|
14 constant |
G |
=
|
110 (Ambient 130 gr/lb -
room 20 gr/lb) |
| F1 |
=
|
2.76 from Table II |
- Factor for moisture difference for
110 gr/lb |
| F2 |
=
|
0.48 from Table III |
- for 48,125 cu.ft. |
| F3 |
=
|
1.0 from Table IV |
- Frame masonry & frame construction |
| F4 |
=
|
0.9 for vapor proof paint on walls &
ceiling, untreated concrete floor |
48,125 x 110 x 2.76 x 0.48 x 1.0 x 0.9 = 450,846 gr/hr
14
|
DOOR LOAD
|
Ohr
x A x G
x F1 = grs/hr
C
|
| Ohr |
=
|
6 openings/hr. |
| A |
=
|
6' x 8' = 48 sq. ft. |
| C |
=
|
7 = constant |
Gr |
=
|
110 gr/lb |
| F1 |
=
|
2.76 |
6 x 48
x 110 x 2.76 = 12,491 gr/hr
7 |
| Ohr |
=
|
4 openings/hr. |
| A |
=
|
3' x 7' = 21 sq. ft. |
| C |
=
|
7 = constant |
Gr |
=
|
110 gr/lb |
| F1 |
=
|
2.76 |
4 x 21
x 110 x 2.76 = 3,643 gr/hr
7 |
FIXED OPENINGS
A
x 300 x G
x F1 = grs/hr
C x D |
| A |
=
|
area, 2.8 sq. ft. |
| 300 |
=
|
Constant (vel. of vapor) |
| C |
=
|
14 Constant |
| D |
=
|
Depth of tunnel = 10' |
G |
=
|
110 gr/lb |
| F1 |
=
|
2.76 |
2.8 x 300 x 110 x 2.76 = 1,822
gr/hr
14 x 10 |

POPULATION LOAD
At a db of 55°F and working at a "light physical exertion" - 1100 gr/hr/person
10 people x 1100 gr = 11,000 gr/hr
TOTAL ROOM MOISTURE LOAD
|
450,846
12,491
3,643
1,822
|
gr/hr
gr/hr
gr/hr
gr/hr
|
- Permeation
- Door Load
- Door Load
- Fixed Opening Load |
|
11,000 gr/hr - Population
Load
|
|
479,802
|
gr/hr
|
TOTAL ROOM LOAD |
The total room latent moisture load is 479,802 gr/hr, which
is added into the calculation below to find the entering grain condition
needed for the space.
Total cfm x (S - G) x 60 = Room load (gr/hr)
14
Total cfm = 24,715 cfm
14 = constant
S = 20 gr/lb. (condition of controlled space)
G = Unknown grain level needed entering space
60 = min/hr
24,715 x (20 - G) x 60 = 479,802 gr/hr.
14
G = 15.4 gr/lb
Thus the air to the room must be 15.4 gr/lb and the air mixture (return
from the room plus the dehumidifier discharge) entering the main system
fan should be 15 gr/lb. to allow for possible leakage into the system
duct work. Here one must resort to trial and error techniques to select
the dehumidifier size.
cfm x (S - G) x 60 = X
14
cfm - 7500 cfm - dehumidifier capacity (trial)
14 = constant
S = 20 gr/lb. condition in the controlled space
G = 4 gr/lb. air leaving dehumidifier (Chart 1, Appendix 4) with entering
air 53°F, 30 gr/lb.
7500 x (20-4) x 60 = 514,285 gr/hr
14
Note that the make-up air of 2400 cfm must mix with 5100 cfm of return
air before entering the dehumidifier.
RECOMMENDATION
The MVB 75E or FLB-12500 Dehumidifier will satisfy the room load conditions
when mixed with the remaining 17,215 cfm of return air and delivered into
the conditioned space the conditioned space.
BRY- AIR DEHUMIDIFIER CALCULATION SHEET
PROJECT: EXAMPLE IV - CONTROLLED HUMIDITY AND TEMPERATURE AREAS
Calculation
Sheet

Example V: PRODUCTION OF
DRY AIR FOR SPECIFIC PURPOSE
Many applications require a specific quantity of outside air to be delivered
at a given moisture content and temperature. This requirement may be a
need to make up air exhausted from a space or to supply air for a process
such as a drying oven.
PHYSICAL FACTS
1. Maximum allowable moisture content - 17 gr/lb of dry air
2. Maximum allowable temperature - 115°F
3. Quantity of air required - 6,000 cfm
4. Maximum condition of outside air - 95°F, 130 gr/lb
From Chart 1, Appendix 4, it is obvious that
130 grain air cannot be reduced to 17 grains in a single pass through
a dehumidifier, without other conditioning. Examination of Chart 1 shows
that to produce 17 grains air leaving the dehumidifier, the inlet condition
should be 64 grains or less at 60°F or less.
This is accomplished as shown above by installing a cooling coil upstream
of the dehumidifier to reduce the temperature and moisture content of
the outside air.
Example VI: WATER TREATMENT
PLANTS
In most water pumping stations, filteration plants, and waste water control
plants, control of humidity in the pipe galleries, pump rooms, and control
rooms is of prime importance. By reducing the dew-point temperature of
the air below the temperature of the piping and walls, sweating and condensation
can be eliminated. By circulating warm, dry air through the areas, water
accumulation is avoided, maintenance for electrical controls, motors,
and instruments is reduced, and paint lasts longer on the pipes, valves,
and flanges.
A standard rule-of-thumb is used to approximate this type of application
load:
Volume of space to be conditioned = CFM dehumidifier
25
(For each 25,000 cu.ft. space, supply 1,000 cfm of dry air.)
The use of an after-cooling coil for the dry air
discharge from the dehumidifier can be omitted in most installations since
the warm, dry air (low rh) will help heat the space during cool or winter
conditions. Heat should not build up to an objectionable level because
the large piping and wall areas are at the same temperature as the water
in the system. Warm air also has the advantage of reducing the rh and
increasing the air's capacity to carry away moisture.
ZERO LEAK SYSTEM FOR A LOW HUMIDITY SPACE
In a system where the ductwork and components are outside
the controlled space, dry air leaving the system will induce the flow
of humid air into the system. If the humid air is not dehumidified, each
cfm will induce a load absorbing the capacity provided by 5 to 10 cfm
of the dehumidified air. If all air that enters the system must pass through
the dehumidifier, the additional load will be reduced by 50 percent or
more. Typical air handling units (AHUs) are not built to be vapor tight.
Standard sheet metal type ductwork has lapped seams that allow leakage.
However, excellent silicone-based sealants are available; for applications
requiring very dry spaces, the seams must be welded shut.
Having a "zero leak" condition means that all air leaving the
controlled space is under positive pressure (to minimize infilteration),
and all the entering air passes through the dehumidifier. The cost of
dehumidification is high when moisture levels must be low. In these situations,
even a small leak can double operating costs. Since ducts are a once-only
expense, attention to ductwork is vital. The other approach to this situation-a
higher capacity dehumidifier- means added costs, year after year.
It is unusual to find air handling units constructed
for zero leak performance. Leaks are anticipated at removable panels,
bearing flanges, drain pans, and through condensate drains with dry traps.
Such units require additional sealing and check valves or positive water
seals on the condensate lines. Cooling devices, especially the coils and
fan, and the filter box need to be handled properly when cleaned, and
they, too, must be tight. Obviously, there are many factors that ban restrict
the zero leak principle.
One way to maximize the chances for a zero leak system is with air treatment
equipment and dehumidifiers designed to fit and operate together effectively.
Buying directly from the equipment manufacturer and not mixing sources
of various equipment components focuses the accountability for moisture
tightness.
Bry-Air constructs custom dehumidifiers and low dew-point AHUs for maximum
efficiency. This extra care in design and construction means zero leak
performance. Proper operating balance compensates for this situation.
When end users, consulting engineers, or other "specifiers"
require a system to be substantially air tight, they means there is no
leakage at any joint.
Assuring zero leak begins in the fabrication and construction stages.
We recommend flanged or gasketed connections with welded seams and joints.
As a minimum, all seams and joints should be caulked. Removable panels
and access doors should be completely enclosed. (Coils will leak where
return bends enter tube sheets.)
Prior to insulting, the system should be tested and deficiencies corrected.
The best method is to use an open flame, if permissible. This requires
candles or other sources of flame. In other situations, smoke devices
or soap suds could be used.
When all these precautions in fabrication, construction, and testing are
complete, the system will perform as designed. Periodic inspection during
operation will allow leaks to be located and corrected.
|